Topological sorting
Order directed dependencies and detect cycles
A monorepo build has packages that depend on generated clients and shared libraries. Alphabetical order is reproducible, but can start a package before its prerequisites exist. Repeatedly trying every possible order is unnecessary too.
Topological sorting tracks which tasks are ready now. When several are ready, this build planner chooses the smallest task ID so the same dependency graph produces the same plan.
Building packages after their prerequisites
A directed edge (u,v) can mean that task u must finish before task v. A topological ordering lists all vertices so every such edge points forward in the list. Build systems, prerequisite courses, and dependency-aware job execution use this model.
Such an ordering exists exactly when the graph has no directed cycle. A cycle means each task in the cycle waits for another task in the same cycle; there is no legal first choice. A topological order need not be unique, so applications often add a tie rule for reproducible results.
Choosing from the currently ready tasks
The indegree of a vertex is the number of incoming edges.
Build adjacency and indegree together, deduplicating before either update:
vertex_count = 4
edges = [(0, 2), (1, 2), (2, 3), (0, 2)]
adjacency = [set() for _ in range(vertex_count)]
indegree = [0] * vertex_count
for u, v in edges:
if v not in adjacency[u]:
adjacency[u].add(v)
indegree[v] += 1
print(indegree)This prints [0, 0, 2, 1]. Counting the repeated 0→2 edge would disagree with the set-backed adjacency. Kahn's method starts with all zero-indegree vertices, emits one, then removes its outgoing prerequisites from the remaining graph. This exercise chooses the smallest currently legal vertex, using a min-heap.
For edges (0,2), (1,2), (2,3):
- Initial indegrees are
[0,0,2,1]; legal frontier is{0,1}. - Emit
0. Vertex2still has one unfinished prerequisite. Frontier:{1}. - Emit
1. Vertex2reaches indegree zero. Frontier:{2}. - Emit
2, then3, producing[0,1,2,3].
The frontier contains exactly the remaining vertices whose prerequisites have all been emitted. Choosing its smallest member gives the lexicographically smallest ordering: any valid ordering sharing the earlier prefix must next choose from that same legal set.
The heap contains legal choices, not all unprocessed vertices:
import heapq
adjacency, indegree = [{2}, {2}, {3}, set()], [0, 0, 2, 1]
frontier = [v for v, count in enumerate(indegree) if count == 0]
heapq.heapify(frontier)
order = []
while frontier:
u = heapq.heappop(frontier)
order.append(u)
for v in adjacency[u]:
indegree[v] -= 1
if indegree[v] == 0:
heapq.heappush(frontier, v)
print(order, len(order) == len(indegree))The output is [0, 1, 2, 3] True. The length check is essential: a stalled frontier can otherwise leave a plausible but incomplete prefix.
Detecting a blocked build
If the frontier becomes empty before all vertices are emitted, a cycle remains. Do not return the partial prefix as though the ordering succeeded. A self-loop is already a cycle. Duplicate edges represent the same prerequisite in this contract and must be counted once; if construction increments indegree twice but later decrements it once, a valid graph will appear cyclic.
The baseline tries task permutations and checks each dependency, potentially exploring V! orders. Adjacency sets and indegree maintenance remove this repeated work. With expected constant-time edge deduplication and a heap frontier, time is O(E+V log(V+1)) and space is O(V+E). Without the smallest-choice requirement, an ordinary queue gives O(V+E) time.
Use topological sorting for ordering constraints, not for shortest paths or choosing the most profitable subset of tasks. A dependency edge does not carry duration information; computing completion times requires additional state. If tasks arrive or dependencies change continuously, rebuilding the order may be sufficient at small scale, while large dynamic graphs need a different design. Independent tasks are still vertices and must appear in the result.
The build planner must report a cycle instead of publishing an incomplete order that merely looks plausible.